Introduction

ITM Platform allows you to perform operations on a group of tasks of a project by navigating to the Tasks section and selecting the tasks you require. The selection is made by ticking the tick box to the left of each task.

As soon as you start making your selection, you can see the number of tasks you selected at the bottom of the list, and four options are enabled.

  • Copy: Copies the selected tasks to another project, as explained in more detail in the next section. Apart from copying tasks, you can choose to include the task members, purchases, revenues, risks, or issues related to the tasks you are copying.
  • Update Status: Select a status from the dropdown list to the left of this option and click on the button “Update Status” to change the status of all selected tasks
  • Delete Task: Deletes all selected tasks. Before deleting the tasks, ITM Platform will ask for your confirmation.

  • Move Dates: This allows to move the start and end date of all selected tasks. The date you select applies to the start date of the earliest of the selected tasks, and the rest of the tasks will be moved within the same number of days.

Copying tasks

 

Clicking the option “Copy” opens a pop-up showing how many tasks will be copied.

Clicking on the option “see which,” you get a list of the selected tasks.

The pop-up allows setting several options that will be applied when copying the list of selected tasks.

 

  • Destination Project: Select the project you want to copy the selected tasks to from a dropdown list of all available projects. By writing in the field, you can filter the list.
  • Dates: The dates of all tasks will automatically be adapted based on the difference in start dates between the origin and destination project.
  • Status: Select the status you want to apply to all tasks copied to the destination project or select “Keep Current” if you want to keep the status unchanged.
  • Priority: Select the priority you want to apply to all tasks copied to the destination project or select “Keep Current” if you want to keep the priority unchanged.
  • Type: Select the type you want to apply to all tasks copied to the destination project or select “Keep Current” if you want to keep the type unchanged.
  • Include descriptions: Select this option to include the task descriptions in the copied tasks.
  • Include dependencies: Select this option to include the relations between predecessor tasks and the copied tasks. Relations between predecessor tasks and copied tasks can only be copied if the predecessor task and the dependent task are included in the list of selected tasks.
  • Include documents: Select this option if you want to include the documents of the copied tasks.
  • Include custom field values: Select this option if you want to include the custom field values of the copied tasks.
  • Include task members: Select this option if you want to include the task members of the copied tasks, as explained in more detail in the below section “Include task members.”
  • Include purchases: Select this option if you want to include the purchases that depend on the selected tasks, as explained in more detail in the “Include purchases” below.
  • Include revenues: Select this option if you want to include the revenues that depend on the selected tasks, as explained in more detail in the “Include revenues” section below.
  • Include risks: Select this option if you want to include the risks that depend on the selected tasks, as explained in more detail in the “Include risks” section below.
  • Include issues: Select this option if you want to include the issues that depend on the selected tasks, as explained in more detail in the “Include issues” below.

Click ” Next ” to proceed once you are happy with the selected options. Before copying the tasks, ITM Platform gives you a summary of the tasks to be copied and a list of warnings, if applicable.

Copiar tareas entre proyectos

The warnings that the pop-up screen can show are:

  • Summary Tasks: ITM Platform will show a warning when you are copying tasks of which the summary tasks are not included in the list of selected tasks. Clicking on “see which,” you can see which Summary Tasks are missing. If you choose to proceed, the tasks will be copied, but without being the child of the summary task.

Advertencia tareas resumen

 

  • Dependencies (Predecessor): This warning will be shown if one or more predecessor tasks are not included in the list of selected tasks, while their dependent tasks are in the list of tasks to be copied. The warning will only be shown if you include the task dependencies.

When you receive warnings on the summary screen, you can either choose to cancel and include additional tasks in the selection to fix these issues or choose to proceed. Once you confirm, the copied tasks may take up to a minute to appear in the destination project.

Include task members

Select this option if you want to include the assigned task members on the tasks to be copied. A section with an additional option is opened when you select the option.

  • Assign team members to the destination project. If you select this option, team members are automatically added to the destination project if they are task members on one or more copied tasks. If the option is unselected, any task member that is not a team member on the destination project will not be included.

Include purchase

Select this option if you want to include the purchases that depend on the tasks to be copied. When you select the option, a section with additional options is opened.

  • Status: Select the status you want to apply to the purchases copied to the destination project or select “Keep Current” if you want to keep the status unchanged.

  • Dates: The due dates of all purchases will automatically be adapted based on the difference in start dates between the origin and destination project.

  • Include descriptions: Select this option to include the descriptions in the copied purchases.

  • Include provider: Select this option if you want to include the provider in the copied purchases.

  • Include documents: Select this option if you want to include the documents of the copied purchases.

  • Include projected amount: Select this option if you want to include the projected amount of the copied purchases. Leave the field on the right empty if you want to copy the amounts of the origin project or set a percentage to multiply the projected amounts with.

  • Include purchase number: Select this option to include the purchase number of the copied purchases.

  • Include actual amount: Select this option to include the actual amount of the copied purchases. Leave the field on the right empty if you want to copy the amounts of the origin project or set a percentage to multiply the actual amounts with.

  • Include custom field values: Select this option if you want to include the custom field values of the copied purchases.

Include revenues

Select this option if you want to include the revenues that depend on the tasks to be copied. When you select the option, a section with additional options is opened.

 

  • Status: Select the status you want to apply to the revenues copied to the destination project or select “Keep Current” if you want to keep the status unchanged.

  • Dates: The due dates of all revenues will automatically be adapted based on the difference in start dates between the origin and destination project.

  • Include descriptions: Select this option to include the descriptions in the copied revenues.

  • Include documents: Select this option if you want to include the documents of the copied revenues.

  • Include projected amount: Select this option if you want to include the projected amount of the copied revenues. Leave the field on the right empty if you want to copy the amounts of the origin project or set a percentage to multiply the projected amounts with.

  • Include revenue no.: Select this option if you want to include the revenue number of the copied revenues.

  • Include actual amount: Select this option if you want to include the actual amount of the copied revenues. Leave the field on the right empty if you want to copy the amounts of the origin project or set a percentage to multiply the actual amounts with.

  • Include custom field values: Select this option if you want to include the custom field values of the copied revenues.

 

Include risks

Select this option to include the risks related to the tasks to be copied. When you select the option, a section with additional options is opened.

 

  • Status: Select the status you want to apply to the risks copied to the destination project or select “Keep Current” if you want to keep the status unchanged.

  • Type: Select the type you want to apply to the risks copied to the destination project or select “Keep Current” if you want to keep the type unchanged.

  • Impact: Select the impact you want to apply to the risks copied to the destination project or select “Keep Current” if you want to keep the impact unchanged.

  • Probability: Select the probability you want to apply to the risks copied to the destination project or select “Keep Current” if you want to keep the probability unchanged.

  • Include documents: Select this option if you want to include the documents of the copied risks.

  • Include descriptions: Select this option to include the descriptions in the copied risks.

  • Include total cost: Select this option if you want to include the total cost of each of the copied risks. Leave the field on the right empty if you want to copy the amount or setting of the origin project or set a percentage to multiply the total cost with.

  • Include total schedule variation: Select this option if you want to include the total schedule variation of each of the copied risks. Leave the field on the right empty if you want to copy the number or set of the origin project or set a percentage to multiply the total schedule variation with.

  • Include change in scope: Select this option if you want to include the change in scope of each of the copied risks.

  • Include mitigation plan: Select this option if you want to include the mitigation plan of each of the copied risks.

  • Include contingency plan: Select this option if you want to include the contingency plan of each of the copied risks.

  • Include the total cost of risk management: Select this option if you want to include each of the copied risks’ total cost of risk management. Leave the field on the right empty if you want to copy the amount or setting of the origin project or set a percentage to multiply the total cost of risk management with.

  • Include total hours of risk management: Select this option if you want to include the total hours of risk management of each of the copied risks. Leave the field on the right empty if you want to copy the number or set of the origin project or set a percentage to multiply the total hours of risk management with.

  • Include risk manager: Select this option to include the assigned risk manager on the risks to be copied. A section with an additional option is opened when you select the option.

 

    • Assign risk manager to destination project: If you select this option, team members are automatically added to the project if they are risk managers on one or more of the copied risks. If the option is unselected, any risk manager that is not a team member on the destination project will not be included.

  • Include custom field values: Select this option if you want to include the custom field values of the copied risks.

 

    Include issues

    Select this option if you want to include the issues related to the tasks to be copied. When you select the option, a section with additional options is opened.

     

      • Status: Select the status you want to apply to the issues copied to the destination project or select “Keep Current” if you want to keep the status unchanged.

      • Type: Select the type you want to apply to the issues copied to the destination project or select “Keep Current” if you want to keep the type unchanged.

      • Include documents: Select this option if you want to include the documents of the copied issues.

      • Include descriptions: Select this option to include the descriptions in the copied issues.

      • Include change in project cost: Select this option if you want to include the change in project cost of each of the copied issues. Leave the field on the right empty if you want to copy the original project’s amount or setting or set a percentage to multiply the change in project cost with.

      • Include change in project schedule: Select this option if you want to include the change in each of the copied issues. Leave the field on the right empty if you want to copy the number or set of the origin project or set a percentage to multiply the change in a project schedule with.

      • Include the cost of issue management: Select this option if you want to include the cost of issue management of each of the copied risks. Leave the field on the right empty if you want to copy the amount or setting of the origin project or set a percentage to multiply the cost of issue management with.

      • Include hours of issue management: Select this option if you want to include the hours of issue management of each copied issue. Leave the field on the right empty if you want to copy the number or set of the origin project or set a percentage to multiply the hours of issue management with.

      • Include issue manager: Select this option if you want to include the assigned issue manager on the issues to be copied. A section with an additional option is opened when you select the option.

     

      • Assign issue manager to destination project: If you select this option, team members are automatically added to the destination project if they are an issue manager on one or more of the copied issues. If the option is unselected, any issue manager that is not a team member on the destination project, will not be included.

    • Include custom field values: Select this option if you want to include the custom field values of the copied issues.