Gantt Chart
A Gantt chart visually represents project tasks, timelines, and dependencies, making it an ideal tool for managing waterfall projects.
Non-working days appear as shaded columns in the chart. These are determined by the project's assigned Working Hours schedule and Holiday Calendar. If the project has no custom calendar, the account defaults are used.
Toolbar
* Create a new task
* Edit a task
* Undo – Redo
* Collapse – Expand all summaries
* Zoom in-out
* Zoom to fit
* Navigate time spans
* Show active baseline
* Create Baseline
* Automatic task scheduling by dependencies (toggles on/off; see Scheduling and recalculation)
* Update selected tasks by dependencies (one time)
* Set task duration based on estimated effort (See the effort-based duration section for more on this)
* Highlight critical path
* Search tasks by name
* Import from MS Project
* Export to PDF
* Export to XML
Contextual menu
When you right-click on a task, a menu will show the various options available, such as edit the task, filter by name, add a task, indent, outdent, or delete.
The availability of some of these options are conditioned to the task’s characteristics:
- Delete is disabled while the task, or any task directly under a summary task, has people assigned. When you save, a task that still has child tasks, time entries, risks, issues, purchases or revenues is not deleted and a message lists the reason.
- The indent option will be available if the previous task can be converted to a summary. It is disabled when the previous task has a team assigned, or when the task is linked to the previous task by a dependency.
- On a task with people assigned, Add sub-task and Convert to milestone are not shown.
- Summary task dates are automatically set based on the dates of the tasks it contains. You cannot manually modify summary task dates, but you can move an entire summary task by dragging it to the desired date. This will move all the tasks contained in the summary task as well.
Columns
You can customize the columns section’s layout (left panel) by right-clicking on any column’s name. You will be presented with various options
- Filter
- Select which columns you want to be displayed
- Sort by one or multiple columns
The available columns are WBS, lock, name, start, finish, sprint, duration, assigned resources, baseline start and end, % done, predecessors, successors, constraint type and date, and status. There is no effort or hours column.
Your column layout is stored in this browser, per interface language, when you save the Gantt. Clearing the browser's site data, or an update of the Gantt, resets it to the default.
Task editing
You can edit a task by selecting it and clicking the edit button in the toolbar, by right-clicking the task and selecting Edit task, or by double-clicking the bar that represents it in the Gantt's right panel. Double-clicking a cell in the left panel does not open the editor: it edits that cell in place.
In the Gantt chart, you can create three types of tasks: task, summary task, and milestone.
Most options display information about the task and are self-explanatory. Nevertheless, some fields require further explanation:
- GENERAL → Effort: read-only field displaying the sum of all user estimated efforts. It does not include the unassigned effort if the task had any.
- GENERAL → Manually scheduled: Checked by default, allow users to schedule the task manually. Unchecked will schedule by dependencies automatically. The checkbox is disabled while automatic scheduling is on for the project.
- RESOURCES : You can set both the percentage and number of hours for each person already assigned to the task. See People and hours in the Gantt.
- ADVANCED : You can apply constraints for your tasks. Whenever you create a task or change its start date, a “Start no earlier than” constraint is set to the task start date. If you remove it, the task will start following its dependencies, or at the project start date if there are no dependencies. The Open task in a new tab link opens the task page.
People and hours in the Gantt
The Gantt plans dates; people and their hours are entered elsewhere.
To see a task's estimated effort or hours from the Gantt, open the task editor: GENERAL shows the total assigned effort and RESOURCES shows each person's hours. The Gantt has no effort or hours column, and an MS Project import brings in no hours or assignments.
- People cannot be added to or removed from a task in the Gantt. Add them in the project Team tab, which also lets you assign many tasks at once, or in the task's Effort tab. See Project team management.
- Only project managers and team members of the project can be assigned to tasks.
- In the task editor's RESOURCES tab, you can change the percentage and hours of the people already assigned. Hours are saved as whole hours, and the change is added to the task's total estimated effort. Milestones and summary tasks have no resources.
- The Assigned Resources column is hidden by default, read-only, and shows avatars.
- The Gantt does not show hours. The task editor shows the assigned effort as a read-only total; unassigned effort and reported hours are not shown. See Effort management.
Scheduling and recalculation
- New projects start with manual scheduling: moving a task does not move the others.
- Turning on Automatic task scheduling by dependencies switches every task that is not completed to automatic scheduling and recalculates their dates. While it is on, bars cannot be dragged. The setting is stored when you save the Gantt.
- Update selected tasks by dependencies recalculates only the selected tasks once, and removes their constraints.
- Summary tasks always take their dates from the tasks they contain.
- Completed tasks are locked: their dates and duration cannot be changed.
- A task with reported time cannot start after its first time entry or end before its last one, unless the account allows time entries outside task dates.
Task dependencies
You can set dependencies between tasks in all their forms (Start-Finish, Start-Start, Finish-Start, Finish-Finish) and set the number of lead or lag days between them.
There are three ways you can do so:
- Hover the start task’s bar and drag the circle to its successor. You can then double click the arrow created between the tasks to edit the dependency.
- Display the predecessor and successor columns and add the task you want to create a dependency to. The columns refer to tasks by their row number. You can add a suffix to indicate the direction of the dependency (SS, SF, FS, FF) plus or minus the number of days in case you need to add a lead or a lag.
- Edit the task and use the tabs Successors and Predecessors.
A task linked by a dependency to the task right above it cannot be indented under it to make that task a summary task.
How to remove dependencies
You can remove dependencies from the Gantt view. Here are two ways:
- Click the arrow that connects the tasks, then click the delete icon.
- Or, right-click the task, go to "edit task," and remove the link from the "Predecessors" or "Successors" tab.
Duration in working days
A task's duration is measured in working days of the project calendar. Task start and finish dates have no time of day, and the Gantt does not store durations in hours: a task lasts at least one day, and milestones have a duration of zero.
Working hours are planned as the estimated effort of each assigned person, in the task editor's RESOURCES tab or in the task's Effort tab. ITM Platform distributes those hours over the task's working days. For a two-hour activity, create a one-day task with two hours of estimated effort. A single day can hold several tasks, each with its own hours, and each person's daily load adds up the hours of all of them.
To link tasks that take place on the same day, use Start-Start (SS) dependencies. With a Finish-Start (FS) dependency, the successor starts on the working day after the predecessor finishes.
Effort-based duration
You can set the task’s duration based on the estimated efforts of the team assigned.
To do so, on Edit task RESOURCES set the percentage of dedication and the number of hours you estimate the task will require for each member. Then, select the task or tasks, and click on the toolbar’s icon “Set task duration based on effort”
. As a result, the task will automatically set the duration to the number of days of the team member that will take longer.
For example, a task has two users, both of which have 40 estimated hours. This setting will make the task duration to be five days. If you change the percentage of one of them to 50%, the task will take ten days.
Progress calculation
Summary tasks and project calculated progress will show the progress according to the progress calculation method applied to the project.
Each summary will have its “% Done” updated when one of the subtasks is updated. Similarly, the “Calculated:” value at the top of the page will also be updated. Note that the “Completed:” value will only be updated when you save with the “Create an automatic progress report” option checked.
Saving and Further Actions
When you save the Gantt chart, you make it available for other users and trigger some other actions:
- Team members will be notified according to their communication preferences
- Estimated hour distribution will be recalculated if need be.
Gantt Import
You can import from MS Project by clicking on the toolbar’s icon “Import from MS Project” and selecting an .mpp file. The tasks and their dependencies will be imported into the Gantt chart, either creating a new plan if the gantt is empty or adding the tasks to the existing plan. The import changes the Gantt on screen; click Save to store it.
When you import an MS Project (.mpp) file into a project that already contains tasks, the system follows these rules: - Tasks are matched by their exact name under the same summary task. If you import the same file twice, nothing changes because the data matches. - If you change dates or durations in MS Project and import again, the matching tasks are updated in the Gantt. - The system adds any new tasks from the file to your Gantt chart alongside the existing ones. A task renamed in either tool is treated as a new task, and tasks missing from the file are not deleted. - Hierarchy matters. The system treats tasks with the same name as different tasks if they are under different summary tasks.
Resources and assignments in the MS Project file are not imported, and neither are its calendars: the project keeps its own working hours and holidays. After importing, add the people to the project team and assign them to tasks in the Team tab.
Gantt Export
You can export your Gantt chart in different formats depending on your needs:
-
Export to PDF:
- Click the toolbar icon “Export to PDF”.
- The PDF will contain the Gantt chart and the task list, depending on the zoom level and the options you have selected.
-
Export to Excel or MS Project:
- Use “Export to Excel” in the task list.
- Make sure to include the task name and start and end dates.
-
Export to XML
- Export the Gantt chart to XML format.
- This file can be imported into MS Project Professional 2013 / 2019. When you try to open the XML as a regular MPP file, the import wizard will automatically open.
Another available option is to share a Gantt snapshot, which is essentially a frozen image or capture of your project's current Gantt chart. It is easily accessible to anyone with the link.