Differences between Tasks, Task-summary and Milestones?
Task: Work specific development or description, may be assigned to teams, or have estimate effort or purchases and revenues added to it.
Task-summary: Groups previous tasks completed, the ITS team and effort will make up a large portion of it.
Milestone: Reference point marking a major event in a project and used to monitor project progress, is dependent on the completion of the tasks predecessor.
THUS, when designing the project you will have to indicate a concrete manner of tasks and specify a set to achieve milestones. THEREFORE, it is necessary to take into account the following aspects:
- specify and list tasks to be performed;
- distribute time for development tasks, indicating start and end dates of each;
- sequencing tasks